Varney's Bridge reopens in Windham following replacement

By Ed Pierce

The contractor replacing Varney's Bridge in Windham has completed work about three weeks ahead of schedule and the bridge has been reopened.

Construction to replace Varney's Bridge on
William Knight Road over the Pleasant River
in Windham has been completed three weeks
ahead of schedule and the bridge has been
reopened. Work to demolish and replace the
aging 26-foot steel girder bridge began there
on June 15. PHOTO BY KEITH MANK
Wyman & Simpson, Inc. started work to demolish and replace the 26-foot steel girder bridge on William Knight Road over the Pleasant River on June 15. Work on the bridge was expected to last until Oct. 13 but was finished last week.

While making repairs on the bridge in 2015, engineers from the Maine Department of Transportation recommended that the town explore options for closing or replacing the bridge because of ongoing structural deterioration. MaineDOT engineers reported that capacity issues and faster and heavier loads stressed this type of bridge past its original design parameters.

Typically, steel girder bridges can be more expensive than other types of bridges because of the rising cost of materials and for construction and this type of bridge may not be suitable for very heavy loads and may not be able to support the weight of heavy vehicles. MaineDOT engineers found issues with the bridge’s concrete abutments and reduced the allowable load to three tons.

That made it not possible for construction trucks, dump trucks, garbage trucks, and other large vehicles to cross the bridge because of the weight limitation. Town snowplows had to stop, turn around and go the other way due to their weight.

With concrete abutments supporting the old steel bridge structure, scouring from the river caused erosion where the concrete touched the Pleasant River water degraded the bridge’s safety. There was also rusting on the steel supports which need to be replaced.

Varney’s Bridge was originally built in 1950 and it had been upgraded and repaired many times over the past three decades with its structural issues persisting and continuing to worsen. In 2021 members of the Windham Town Council voted to replace the existing bridge with the most cost-effective method to ensure the safety of the community upon the recommendation of the town manager. At the Annual Windham Town Meeting in June 2021, Windham residents approved spending $25,000 for a study at the Annual Town Meeting about how to best move forward to replace the aging structure.

The study was completed in the summer of 2022, and the results were forwarded to the MaineDOT. Using the MaineDOT Bridge Program Design Guide, a preliminary design report was created and mandated that any other survey work needed to define right-of-way and bridge layout and alignment be performed and any geotechnical engineering evaluations required to design a new bridge support structure be initiated.

In January 2023, the new Maine DOT Three-Year Plan for upcoming projects by state crews was released. MaineDOT authorized $1.5 million in funding for the $2.2 million project with the town picking up the remaining $700,000 for the project.

The Town of Windham then developed preliminary and final design plans in accordance with MaineDOT standards and requirements. Those design plans included a specific plan for the project, a bridge profile including cross-sections and geometry for approach design, design computations, load ratings, and evaluation information for the new structure meeting MaineDOT specifications. All of that included development of an engineering estimate of construction costs and creating a final plan for review by the state. 

At Windham’s Annual Town Meeting in June 2023, a warrant item was approved by voters to contribute $700,000 to complete the bridge replacement project. MaineDOT also conducted and documented quality control design checks and provided engineering support during the competitive bidding process and any other additional services as was requested by the town.

Windham Town Councilors put the project out to bidding in November 2025 and awarded the project to Wyman & Simpson, Inc. for the town’s portion of costs in general obligation bond funding for replacing Varney’s Bridge. Seven bids had been submitted to replace the bridge.

When the bridge work started in June 2026 it was estimated at the time it could take up to 120 days to complete. The reconstruction work required a full road closure on William Knight Road and local detours were put in place for traffic and emergency vehicles.

The bridge was reopened to the public on Sept. 17. <

Friday, April 4, 2025

State unveils upcoming MDOT local projects under Three Year Plan

By Ed Pierce

Some ambitious roadwork and construction projects are nearing for residents of Windham and Raymond.

Varney's Bridge on William Knight Road over
the Pleasant River in Windham will be replaced
by the Maine Department of Transportation this
summer at a cost of $2 million as part of MDOT's
Three Year Plan. PHOTO BY ED PIERCE 
Earlier this week, State Senator Tim Nangle of Windham, unveiled details of Maine’s three-year transportation infrastructure work plan, and what it means for Senate District 26, including here in the Lakes Region.

MDOT’s Three-Year Plan is released annually with an outline of the Maine Department of Transportation’s strategy for road, bridge and other transportation upgrades and maintenance projects.

According to the Maine DOT, this year’s three-year work plan makes a historic $4.8 billion investment in construction and maintenance of transportation infrastructure across the state. It includes 2,716 individual work items for the calendar years 2025, 2026 and 2027.

In 2025 and 2026, the Maine DOT will undertake numerous projects to improve transportation in Senate District 26, including significant investments in paving, safety improvements and planning for expanded transit and pedestrian access across Windham and neighboring communities.

Additionally, there will be improvements to the Frye Island Ferry Service in Raymond.

“As Chair of the Transportation Committee, I’m proud to see meaningful investments coming to the communities I represent,” Nangle said. “Whether it’s paving roads in Windham or improving transit planning in Westbrook, this work plan helps strengthen the connections our families, businesses and towns rely on every day.”

The following are planned capital and maintenance work by MDOT for communities in Senate District 26 in 2025:

Bridge and Structural Maintenance

** Varney’s Bridge: Located on William Knight Road over the Pleasant River. Bridge Replacement.

** Windham [and Gorham]: Great Falls #1 (Long) Bridge (#6210) over the Presumpscot River, located 0.04 of a mile east of the Gorham town line, and Great Falls #2 Bridge (#1529) over the Presumpscot River, located on the Gorham-Windham town line.

** Windham: Pleasant River Bridge (#2676) over the Pleasant River, located 0.16 of a mile north of Hall Road.

Ferry

** Raymond and Frye Island: Capital improvements to the Frye Island Ferry Service between Raymond and Frye Island.

Highway Construction/Rehabilitation

** Windham: Beginning 0.45 of a mile west of Outpost Drive, and extending west 0.14 of a mile, including the roundabout intersection with Route 202.

Highway Paving

** Windham: Beginning at Depot Street and extending north 0.74 of a mile.

Highway Safety and Spot Improvements


** Windham: Beginning 0.01 of a mile south of Swett Road and extending north 0.57 of a mile.

Maine Department of Transportation Commissioner Bruce A. Van Note said that development of a plan of this scope is a complicated endeavor.

“Over the course of months, skilled public servants with hundreds of years of combined experience analyze asset management needs, the availability and use limitations of various funding sources, policy priorities, stakeholder input, project delivery capacity, supplemental funding needs for existing projects, and finally the addition of new work and projects,” he said. “I am humbled to work with the talented and dedicated people who embrace one of the toughest jobs you’ll ever love.”

Of all these tasks, estimating available funding may be the most humbling, Van Note said.

“Until recently, MaineDOT was largely forced into ‘MacGyver mode,’ using flagging dedicated revenues from fuel taxes and vehicle fees and general obligation bonding to do the best we could with what we had, which resulted in us competently managing the slow decline of the transportation system,” he said. “This challenge was exacerbated by historic construction cost increases over the last six years, as evidenced by the 70-percent increase in the national construction price index. This inflation resulted in the need for significantly more funding just to do an inadequate level of work. Thankfully, bipartisan policy action at both the federal and state levels in recent years has allowed MaineDOT to pivot from making do to making progress.”

View the entire 2025-2026-2027 Three-Year MDOT Work Plan at www.mainedot.gov. <